Question 10
An administrator wants to verify that the intended control is working in this EPM situation: A project exception granted elevated installer access for a pilot but remains active after the pilot finishes. Which evidence provides the strongest case-specific verification?
Explanation
Correct Answer
Deactivate the obsolete policy or formally renew it with bounded scope and documented need. Privilege exception lifecycle needs expiry and recertification. Verify post-expiry privilege denial and continued legitimate production operation.
Incorrect Answers
A plan describes intent, but it does not prove the corrective control operates. Relevant acceptance evidence: Verify post-expiry privilege denial and continued legitimate production operation.
“An unrelated successful audit of policy priority conflict: Inspect triggered policy evidence on the affected agent and compare rule evaluation.” is not sufficient evidence of the specified recovery. Deactivate the obsolete policy or formally renew it with bounded scope and documented need. Verify post-expiry privilege denial and continued legitimate production operation.
Console availability cannot establish application privilege or policy behavior on the affected endpoint. Verify instead: Verify post-expiry privilege denial and continued legitimate production operation.